Mounting The Flashings
Starting at the left hand side mount the top ashing ensuring that the leading edge hooks under
the wind retaining rail. When located correctly you will not be able to lift the leading edge by hand.
Secure in place using 1 x (4x30mm) wood screws (this screw needs to be located as indicated so as
not to compromise the water tightness of the ashings.
Leading Edge
Section 4 - In Roof Frame Installation